Market Notices

118645MINIMUM SYSTEM LOAD07/10/2024 02:49:02 PM

STPASA - Forecast Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs 13/10/2024 to 1400 hrs 13/10/2024.

Minimum regional demand is forecast to be 1623 MW at 1300 hrs, and the advisory threshold is:

o MSL1 - 1865 MW
o MSL2 - 1365 MW
o MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

AEMO Operations
     
118643NON-CONFORMANCE07/10/2024 01:10:15 PM

NON-CONFORMANCE Region VIC1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STOCKYD1
Duration: 07/10/2024 11:25 to 07/10/2024 13:10
Amount: 101 MW
Constraint: NC-V_STOCKYD1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118638NON-CONFORMANCE07/10/2024 10:15:28 AM

NON-CONFORMANCE Region NSW1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WAGGNSF1
Duration: 07/10/2024 09:55 to 07/10/2024 10:15
Amount: 49 MW
Constraint: NC-N_WAGGNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118635NON-CONFORMANCE06/10/2024 11:32:58 PM

NON-CONFORMANCE Region SA1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 6 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LKBONNY2
Duration: 06/10/2024 23:05 to 06/10/2024 23:10
Amount: 73 MW
Constraint: NC-S_LKBONNY2

Manager NEM Real Time Operations
     
118631NON-CONFORMANCE06/10/2024 01:25:28 PM

NON-CONFORMANCE Region NSW1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 6 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 06/10/2024 13:00 to 06/10/2024 13:25
Amount: 9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118627NON-CONFORMANCE06/10/2024 08:20:19 AM

NON-CONFORMANCE Region QLD1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 05/10/2024 20:05 to 06/10/2024 08:20
Amount: -56 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118624NON-CONFORMANCE05/10/2024 07:15:20 PM

NON-CONFORMANCE Region QLD1 Saturday, 5 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 05/10/2024 18:45 to 05/10/2024 19:15
Amount: 37 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118608NON-CONFORMANCE05/10/2024 11:05:23 AM

NON-CONFORMANCE Region NSW1 Saturday, 5 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WYASF1
Duration: 05/10/2024 10:30 to 05/10/2024 11:05
Amount: 31 MW
Constraint: NC-N_WYASF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118598MARKET SYSTEMS04/10/2024 04:07:21 PM

CHG0098496 | Production | QLD Marketnet Router Replacement

Change Number: CHG0098496
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement
Change Start Date & Time: 19/10/2024 14:00:53 AEST
Change End Date & Time: 19/10/2024 19:00:53 AEST

Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on the 19th October 2024:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.

** FAILURE TO ENSURE VPN FAILOVER WILL RESULT IN LOSS OF MARKETNET CONNECTIVITY **
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .


     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm