NON-CONFORMANCE Region NSW1 Monday, 12 February 2024
NON-CONFORMANCE NSW1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: RIVNBG2, RIVNBL2
Aggregate Dispatch Group: RESS2_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 50 MW
Constraint: NC-N_RESS2_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 12 February 2024
NON-CONFORMANCE NSW1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202402112030_review] Prices for interval 11-Feb-2024 20:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 2025 hrs on 11 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Feb-2024 20:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402112025_review] Prices for interval 11-Feb-2024 20:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 2020 hrs on 11 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Feb-2024 20:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402112020_review] Prices for interval 11-Feb-2024 20:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 2015 hrs on 11 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Feb-2024 20:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402112015_review] Prices for interval 11-Feb-2024 20:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 2010 hrs on 11 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Feb-2024 20:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402112010_review] Prices for interval 11-Feb-2024 20:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 2005 hrs on 11 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Feb-2024 20:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402112005_review] Prices for interval 11-Feb-2024 20:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 11 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Feb-2024 20:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 04/02/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 04/02/2024
Refer Market Notice 114245
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs 11/02/2024
Manager NEM Real Time Operations