Market Notices

120517RECLASSIFY CONTINGENCY15/11/2024 06:24:04 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 15/11/2024 18:23

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120478

Auto-generated on behalf of Manager NEM Real Time Operations
     
120516RECLASSIFY CONTINGENCY15/11/2024 05:34:50 PM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 15/11/2024 17:34 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120509PRICES SUBJECT TO REVIEW15/11/2024 04:50:15 PM

[EventId:202411151655_review] Prices for interval 15-Nov-2024 16:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1650 hrs on 15 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120508PRICES SUBJECT TO REVIEW15/11/2024 04:45:20 PM

[EventId:202411151650_review] Prices for interval 15-Nov-2024 16:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120507PRICES SUBJECT TO REVIEW15/11/2024 04:40:23 PM

[EventId:202411151645_review] Prices for interval 15-Nov-2024 16:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1640 hrs on 15 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120506PRICES SUBJECT TO REVIEW15/11/2024 04:35:25 PM

[EventId:202411151640_review] Prices for interval 15-Nov-2024 16:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1635 hrs on 15 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120504PRICES SUBJECT TO REVIEW15/11/2024 04:30:25 PM

[EventId:202411151635_review] Prices for interval 15-Nov-2024 16:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120503PRICES SUBJECT TO REVIEW15/11/2024 04:25:18 PM

[EventId:202411151630_review] Prices for interval 15-Nov-2024 16:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1625 hrs on 15 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120489PRICES SUBJECT TO REVIEW15/11/2024 12:00:18 PM

[EventId:202411151205_review] Prices for interval 15-Nov-2024 12:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 15 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 12:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm