Filter by category
Filter by Date
Network Augmentation Commissioned - NSW Region - 31/10/2024
Network Augmentation Commissioned - NSW Region - 31/10/2024
At 1200 hrs 31/10/2024, the Buronga No.4 330kV synchronous condenser has been commissioned.
Manager NEM Real Time Operations
Fast Frequency Response Market - Increase in R1 FCAS dispatch caps from 4th November 2024
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 4th November AEMO will increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 350 MW to 375 MW
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
[EventId:202410301600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 October 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 30 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 October 2024.
Refer to market notice: 119683
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 30 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410301505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 October 2024 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 30 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 30 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update - Lightning vulnerable lines in Vic region
Update - Lightning vulnerable lines in Vic region
Refer to AEMO Electricity Market Notice 119029
At 1525 hrs on 18/10/2024 the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line tripped and auto-reclosed.
The cause of the trip was identified as due to Lightning.
In accordance with SO_OP_3715, AEMO now considers the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line to be vulnerable with a category of probable due to Lightning.
Manager NEM Real Time Operations
Update - Pre dispatch demand forecast - Qld region
Update - Pre dispatch demand forecast - Qld region
Refer market notice: 119666
The issue relating to the Queensland Pre dispatch demand forecast has been resolved.
Manager NEM Real Time Operations
Pre dispatch demand forecast - Qld region
Pre dispatch demand forecast - Qld region
AEMO is aware of an error in the Queensland pre dispatch demand forecast.
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.
Manager NEM Real Time Operations
[EventId:202410291745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 October 2024 17:45
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 29 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Refer to market notice: 119664
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 29 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410291710_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 17:10
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1710 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.