NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024
NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 01/02/2024 12:25 to 01/02/2024 13:45
Amount: -44 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114017 is cancelled at 1400 hrs 31/01/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114019 has been updated at 1400 hrs 31/01/2024 to the following:
1. From 1400 hrs to 1630 hrs 05/02/2024.
The forecast capacity reserve requirement is 1462 MW.
The minimum capacity reserve available is 905 MW.
2. From 1700 hrs to 2000 hrs 05/02/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 995 MW.
AEMO Operations
Update - Direction - SA Region - 28/01/2024
Update - Direction - SA Region - 28/01/2024
Refer Market Notice 113930
The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114021 has been updated at 1400 hrs 31/01/2024 to the following:
1. From 1400 hrs to 1730 hrs 06/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 813 MW.
2. From 1900 hrs to 2100 hrs 06/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 892 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114023 is cancelled at 1400 hrs 31/01/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114024 has been updated at 1400 hrs 31/01/2024 to the following:
From 1730 hrs to 2000 hrs 06/02/2024.
The forecast capacity reserve requirement is 1267 MW.
The minimum capacity reserve available is 944 MW.
AEMO Operations
NON-CONFORMANCE Region QLD1 Wednesday, 31 January 2024
NON-CONFORMANCE QLD1 Region Wednesday, 31 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 31/01/2024 09:35 to 31/01/2024 09:45
Amount: 40 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Direction - SA Region - 28/01/2024
Update - Direction - SA Region - 28/01/2024
Refer Market Notice 113930
The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations