STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119746 has been updated at 1400 hrs 02/11/2024 to the following:
1. From 1800 hrs to 1900 hrs 04/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 916 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119744 has been updated at 1400 hrs 02/11/2024 to the following:
1. From 1700 hrs to 1730 hrs 07/11/2024.
The forecast capacity reserve requirement is 867 MW.
The minimum capacity reserve available is 840 MW.
2. From 1900 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 655 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119754 has been updated at 1400 hrs 02/11/2024 to the following:
From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 140 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119762 has been updated at 1400 hrs 02/11/2024 to the following:
[1.] From 1530 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 142 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119747 has been updated at 1400 hrs 02/11/2024 to the following:
1. From 1330 hrs to 1530 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 834 MW.
2. From 1900 hrs to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.
Manager NEM Real Time Operations
STPASA - Update of the forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119755 has been updated at 0940 hrs 02/11/2024 to the following:
[1.] From 1600 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 178 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 04/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119753 is cancelled at 0930 hrs 02/11/2024.
Manager NEM Real Time Operations
STPASA - Update of the forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119751 has been updated at 0800 hrs 02/11/2024 to the following:
[1.] From 1800 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 470 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119752 has been updated at 0530 hrs 02/11/2024 to the following:
From 1800 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 378 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.