Market Notices

117537MARKET INTERVENTION02/08/2024 02:48:59 PM

Cancellation - AEMO Intervention Event - SA region 01/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 01/08/2024

Refer to Market Notice 117525

The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 02/08/2024.



Manager NEM Real Time Operations
117536MARKET INTERVENTION02/08/2024 02:38:20 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 117529

Direction is cancelled from: 1430 hrs 02/08/2024

Manager NEM Real Time Operations
117535MARKET INTERVENTION02/08/2024 12:49:55 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 117526

Direction is cancelled from: 1230 hrs 02/08/2024

Manager NEM Real Time Operations
117532MARKET INTERVENTION02/08/2024 12:53:59 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 117531

Direction is cancelled from: 0105 hrs 02/08/2024

Manager NEM Real Time Operations
117531MARKET INTERVENTION02/08/2024 12:38:11 AM

Direction - SA region 02/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 02/08/2024

Refer to Market Notice 117521


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 0030 hrs 02/08/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0035 hrs 02/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0135 hrs 02/08/2024 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
117529MARKET INTERVENTION01/08/2024 05:00:00 PM

Direction - SA region 01/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 01/08/2024

Refer to Market Notice 117521


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 01/08/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 2230 hrs 01/08/2024
Services provided: Voltage Control
Circumstances necessitating the direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 1430 hrs 02/08/2024

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
117526MARKET INTERVENTION01/08/2024 04:01:04 PM

Direction - SA region 01/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 01/08/2024

Refer to Market Notice 117521


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 01/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0000 hrs 02/08/2024
Services provided: Voltage Control
Circumstances necessitating the direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 1230 hrs 02/08/2024 / further notice.

Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
117525MARKET INTERVENTION01/08/2024 03:59:16 PM

Direction - SA region 01/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 01/08/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 01/08/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
117524MARKET INTERVENTION01/08/2024 02:54:45 PM

Cancellation - AEMO Intervention Event - SA region 31/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 31/07/2024

Refer to Market Notice 117515

The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 01/08/2024.



Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm