Market Notices

119630SETTLEMENTS RESIDUE29/10/2024 12:33:14 PM

[EventId:202410291230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 October 2024 12:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 29 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.

Refer to market notice: 119627

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 29 October 2024.

This is an AEMO autogenerated Market Notice.
     
119627SETTLEMENTS RESIDUE29/10/2024 11:40:16 AM

[EventId:202410291140_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 11:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1140 hrs on 29 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1140 hrs on 29 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119612SETTLEMENTS RESIDUE29/10/2024 10:02:06 AM

[EventId:202410291000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 October 2024 10:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 29 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.

Refer to market notice: 119609

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1000 hrs on 29 October 2024.

This is an AEMO autogenerated Market Notice.
     
119609SETTLEMENTS RESIDUE29/10/2024 09:05:17 AM

[EventId:202410290905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 09:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0905 hrs on 29 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 29 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119606SETTLEMENTS RESIDUE29/10/2024 06:25:18 AM

[EventId:202410290625_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 29 October 2024 06:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0625 hrs on 29 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 October 2024.

Refer to market notice: 119605

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0625 hrs on 29 October 2024.

This is an AEMO autogenerated Market Notice.
     
119605SETTLEMENTS RESIDUE29/10/2024 01:30:25 AM

[EventId:202410290130_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 29 October 2024 01:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0130 hrs on 29 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 0130 hrs on 29 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119603SETTLEMENTS RESIDUE28/10/2024 07:00:22 PM

[EventId:202410281900_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 28 October 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 28 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.

Refer to market notice: 119600

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1900 hrs on 28 October 2024.

This is an AEMO autogenerated Market Notice.
     
119600SETTLEMENTS RESIDUE28/10/2024 06:00:22 PM

[EventId:202410281800_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 28 October 2024 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 28 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1800 hrs on 28 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119599SETTLEMENTS RESIDUE28/10/2024 04:20:29 PM

[EventId:202410281620_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 28 October 2024 16:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1620 hrs on 28 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 October 2024.

Refer to market notice: 119587

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1620 hrs on 28 October 2024.

This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm