117053INTER-REGIONAL TRANSFER18/06/2024 03:19:21 PM

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

A planned outage of Collector Wind Farm to Yass 3L 330kV line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 08/07/2024.

The outage has been completed and Collector Wind Farm to Yass 3L 330kV line returned to service at 1515 hrs 18/06/2024

Constraint set revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
116998PRICES SUBJECT TO REVIEW14/06/2024 02:35:16 PM

[EventId:202406141440_review] Prices for interval 14-Jun-2024 14:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116995PRICES SUBJECT TO REVIEW14/06/2024 02:30:19 PM

[EventId:202406141435_review] Prices for interval 14-Jun-2024 14:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116994PRICES SUBJECT TO REVIEW14/06/2024 02:25:23 PM

[EventId:202406141430_review] Prices for interval 14-Jun-2024 14:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1425 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116993PRICES SUBJECT TO REVIEW14/06/2024 02:20:23 PM

[EventId:202406141425_review] Prices for interval 14-Jun-2024 14:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116992PRICES SUBJECT TO REVIEW14/06/2024 02:15:19 PM

[EventId:202406141420_review] Prices for interval 14-Jun-2024 14:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1415 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116991PRICES SUBJECT TO REVIEW14/06/2024 02:10:24 PM

[EventId:202406141415_review] Prices for interval 14-Jun-2024 14:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1410 hrs on 14 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116956PRICES SUBJECT TO REVIEW11/06/2024 06:10:22 PM

[EventId:202406111815_review] Prices for interval 11-Jun-2024 18:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1810 hrs on 11 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 18:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116954PRICES SUBJECT TO REVIEW11/06/2024 06:05:21 PM

[EventId:202406111810_review] Prices for interval 11-Jun-2024 18:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 11 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 18:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.