Market Notices

120382RECLASSIFY CONTINGENCY13/11/2024 05:49:10 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 13/11/2024 17:49

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 120342

Auto-generated on behalf of Manager NEM Real Time Operations
     
120380RECLASSIFY CONTINGENCY13/11/2024 05:29:21 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 13/11/2024 17:29 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
120379RECLASSIFY CONTINGENCY13/11/2024 05:19:10 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 13/11/2024 17:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 120339

Auto-generated on behalf of Manager NEM Real Time Operations
     
120375PRICES UNCHANGED13/11/2024 03:42:30 PM

[EventId:202411131515_confirmed] Prices for interval 13-Nov-2024 15:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 15:15.

In accordance with Market Notice 120362 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120374PRICES UNCHANGED13/11/2024 03:40:36 PM

[EventId:202411131535_confirmed] Prices for interval 13-Nov-2024 15:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 15:35.

In accordance with Market Notice 120369 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120373PRICES UNCHANGED13/11/2024 03:39:19 PM

[EventId:202411131530_confirmed] Prices for interval 13-Nov-2024 15:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 15:30.

In accordance with Market Notice 120368 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120372PRICES UNCHANGED13/11/2024 03:38:09 PM

[EventId:202411131525_confirmed] Prices for interval 13-Nov-2024 15:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 15:25.

In accordance with Market Notice 120366 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120371PRICES UNCHANGED13/11/2024 03:35:21 PM

[EventId:202411131520_confirmed] Prices for interval 13-Nov-2024 15:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 15:20.

In accordance with Market Notice 120364 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120370PRICES UNCHANGED13/11/2024 03:36:57 PM

[EventId:202411131510_confirmed] Prices for interval 13-Nov-2024 15:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 13 November 2024

PRICES ARE NOW CONFIRMED for trading interval 13-Nov-2024 15:10.

In accordance with Market Notice 120361 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm