Market Notices

119020NON-CONFORMANCE18/10/2024 11:25:22 AM

NON-CONFORMANCE Region VIC1 Friday, 18 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 18 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BULBES1
Duration: 18/10/2024 11:05 to 18/10/2024 11:25
Amount: 20 MW
Constraint: NC-V_BULBES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119018MARKET SYSTEMS18/10/2024 08:38:58 AM

CHG0098658 | Completed | Production | Planned System Maintenance - Declared Wholesale Gas Market (DWGM)

Change Number: CHG0098658

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: DWGM - Web Exchanger

Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118965NON-CONFORMANCE17/10/2024 07:35:25 AM

NON-CONFORMANCE Region VIC1 Thursday, 17 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 17 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 17/10/2024 07:25 to 17/10/2024 07:35
Amount: -53 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
     
118934MARKET SYSTEMS16/10/2024 03:56:26 PM

CHG0098812 | Completed | Pre-Production | Pre-Prod MSATS and eMDM November Maintenance Release

Change Number: CHG0098812

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Market Settlement & Transfer System

Change Title: Pre-Prod MSATS and eMDM November Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118923NON-CONFORMANCE16/10/2024 07:35:21 AM

NON-CONFORMANCE Region QLD1 Wednesday, 16 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 16 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WOOLGSF1
Duration: 16/10/2024 06:55 to 16/10/2024 07:35
Amount: 112 MW
Constraint: NC-Q_WOOLGSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118911MARKET SYSTEMS15/10/2024 01:53:48 PM

CHG0098814 | Production | MSATS and eMDM November Maintenance Release

Change Number: CHG0098814

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: MSATS and eMDM November Maintenance Release

Change Start Date & Time: 27/10/2024 10:00:00 AEST
Change End Date & Time: 27/10/2024 17:00:00 AEST
Outage Start Date & Time: 27/10/2024 10:00:00 AEST
Outage End Date & Time: 27/10/2024 14:00:00 AEST

Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
     
118895NON-CONFORMANCE15/10/2024 07:30:12 AM

NON-CONFORMANCE Region QLD1 Tuesday, 15 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 15 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: PUMP2
Duration: 15/10/2024 07:25 to 15/10/2024 07:30
Amount: 245 MW
Constraint: NC-Q_PUMP2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118861NON-CONFORMANCE13/10/2024 11:20:22 PM

NON-CONFORMANCE Region QLD1 Sunday, 13 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 13 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 13/10/2024 22:50 to 13/10/2024 23:20
Amount: -65 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118860NON-CONFORMANCE13/10/2024 06:10:16 PM

NON-CONFORMANCE Region QLD1 Sunday, 13 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 13 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 13/10/2024 18:00 to 13/10/2024 18:10
Amount: 29 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm