121763MARKET INTERVENTION12/12/2024 09:30:08 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121722

Direction is cancelled from: 0930 hrs 12/12/2024

Manager NEM Real Time Operations
     
121762RESERVE NOTICE12/12/2024 09:05:57 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121735 has been updated at 0800 hrs 12/12/2024 to the following:

1. From 1400 hrs to 1500 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 239 MW.

2. From 1930 hrs to 2100 hrs 16/12/2024.
The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 136 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121755NON-CONFORMANCE12/12/2024 05:40:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 12 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 12 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 12/12/2024 05:35 to 12/12/2024 05:40
Amount: -31 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
     
121736RESERVE NOTICE12/12/2024 12:55:44 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:

[1.] From 1700 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 578 MW.
The minimum capacity reserve available is 207 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121735RESERVE NOTICE12/12/2024 12:40:55 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1500 hrs 16/12/2024 to 1530 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 295 MW.

[2.] From 1600 hrs 16/12/2024 to 1700 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 40 MW.

[3.] From 1830 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121729RESERVE NOTICE11/12/2024 08:46:54 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1500 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 755 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121723RESERVE NOTICE11/12/2024 04:03:08 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121711 has been updated at 1500 hrs 11/12/2024 to the following:

1. From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 690 MW.

2. From 1630 hrs 16/12/2024 to 1930 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 292 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121722MARKET INTERVENTION11/12/2024 04:07:36 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121721


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 11/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 12/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0930 hrs 12/12/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
121721MARKET INTERVENTION11/12/2024 04:05:19 PM

Direction - SA region 11/12/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 11/12/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 11/12/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.