122449MARKET INTERVENTION24/12/2024 04:30:47 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122441

Direction is cancelled from: 1630 hrs 24/12/2024

Manager NEM Real Time Operations
     
122448MARKET INTERVENTION24/12/2024 01:54:13 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122440

Direction is cancelled from: 1400 hrs 24/12/2024

Manager NEM Real Time Operations
     
122447MARKET INTERVENTION24/12/2024 11:31:06 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 122446

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 24/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 24/12/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
122446MARKET INTERVENTION24/12/2024 10:57:43 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 24/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
122443SETTLEMENTS RESIDUE23/12/2024 05:00:33 PM

[EventId:202412231700_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 December 2024 17:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 23 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 December 2024.

Refer to market notice: 122438

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1700 hrs on 23 December 2024.

This is an AEMO autogenerated Market Notice.
     
122441MARKET INTERVENTION23/12/2024 04:34:00 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122408

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 24/12/2024.

The direction update is issued at 1630 hrs 23/12/2024.

Manager NEM Real Time Operations
     
122440MARKET INTERVENTION23/12/2024 04:32:51 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122407

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 24/12/2024.

The direction update is issued at 1630 hrs 23/12/2024.

Manager NEM Real Time Operations
     
122438SETTLEMENTS RESIDUE23/12/2024 03:45:34 PM

[EventId:202412231545_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 December 2024 15:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 23 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1545 hrs on 23 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122434RECLASSIFY CONTINGENCY23/12/2024 05:39:21 AM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 23/12/2024 05:39

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 122428

Auto-generated on behalf of Manager NEM Real Time Operations
     