Market Notices

117546INTER-REGIONAL TRANSFER04/08/2024 10:56:12 AM

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.

The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024

Constraint set(s) revoked: V-KTSM_R

Manager NEM Real Time Operations
117496INTER-REGIONAL TRANSFER28/07/2024 11:42:01 AM

Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/07/2024

A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0830 hrs 26/07/2024 to 1730 hrs 28/07/2024.

The outage has been extended until 1200 hrs 29/07/2024

Constraint set(s) invoked:
I-HYSE
I-VS_050
I-VS+LKB_050

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117449INTER-REGIONAL TRANSFER25/07/2024 03:53:00 PM

Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024

A planned outage of Heywood M1 Transformer in the VIC region was scheduled from 0600 hrs 25/07/2024 to 1800 hrs 25/07/2024.

The outage has been completed and Heywood M1 Transformer returned to service at 1550 hrs 25/07/2024

Constraint set(s) revoked: V-HYTX_M12

Manager NEM Real Time Operations
117448INTER-REGIONAL TRANSFER25/07/2024 03:46:44 PM

Inter-regional transfer limit variation - Keilor - Sth Morang 500kV Line - VIC region - 25/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Keilor - Sth Morang 500kV Line - VIC region - 25/07/2024

A planned outage of Keilor - Sth Morang 500kV Line ] in the VIC region was scheduled from 0700 hrs 25/07/2024 to 1630 hrs 25/07/2024.

The outage has been completed and Keilor - Sth Morang 500kV Line returned to service at 1450 hrs 25/07/2024

Constraint set(s) revoked: V-KTSM_R

Manager NEM Real Time Operations
117411INTER-REGIONAL TRANSFER22/07/2024 09:50:31 AM

Inter-regional transfer limit variation - Heywood - South East 1 275 kV Line - SA region - 22/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood - South East 1 275 kV Line - SA region - 22/07/2024

A planned outage of Heywood - South East 1 275 kV Line in the SA region was scheduled from 0930 hrs 22/07/2024 to 1700 hrs 22/07/2024.

The outage has been cancelled.

Constraint set(s) revoked:
I-HYSE
I-VS+LKB_050
I-VS_050
S-SECB6611_10
S-SE_1CP

Manager NEM Real Time Operations
117389INTER-REGIONAL TRANSFER20/07/2024 02:52:46 PM

Inter-regional transfer limit variation - Armidale Coffs Harbour 96C 132kV LINE - NSW region - 20/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale Coffs Harbour 96C 132kV LINE - NSW region - 20/07/2024

At 1422 hrs 20/07/2024 there was an unplanned outage of Armidale Coffs Harbour 96C 132kV LINE.

The following constraint set(s) invoked at 1430 hrs 20/07/2024
N-ARCH_96C

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117381INTER-REGIONAL TRANSFER20/07/2024 01:03:16 PM

Inter-regional transfer limit variation - Mitchell Singleton 95X 132kV LINE- NSW region - 20/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Mitchell Singleton 95X 132kV LINE- NSW region - 20/07/2024

At 1117 hrs 20/07/2024 there was an unplanned outage of Mitchell Singleton 95X 132kV LINE.

The following constraint set(s) invoked at 1250 hrs 20/07/2024
N-NIL_RBKU_CLOSED
N-LDTM_82_CL

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117375INTER-REGIONAL TRANSFER19/07/2024 07:03:12 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 117372

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1835 hrs.

Manager NEM Real Time Operations
117374INTER-REGIONAL TRANSFER19/07/2024 06:01:53 PM

Inter-regional transfer limit variation - Heywood interconnector - SA and Vic regions - 19/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood interconnector - SA and Vic regions- 19/07/2024

Refer to reclassification Market notice 117373

The following constraint set(s) invoked at 1740 hrs 19/07/2024
I-SV_250 , I-VS_250

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm