Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112137 is cancelled at 1850 hrs 09/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1344 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 05/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112016 is cancelled at 1845 hrs 05/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1350 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 02/12/2023
Cancellation of Actual (LOR1) condition in the QLD region - 02/12/2023
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.111943 is cancelled at 1945 hrs 02/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 02/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 02/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1820 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 1299 MW
The minimum capacity reserve available is 1167 MW
Manager NEM Real Time Operations