[EventId:202503151635_review] Prices for interval 15-Mar-2025 16:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503151630_review] Prices for interval 15-Mar-2025 16:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503151625_review] Prices for interval 15-Mar-2025 16:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503151620_review] Prices for interval 15-Mar-2025 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125665 has been updated to the following:
[1.] From 1630 hrs 16/03/2025 to 1900 hrs 16/03/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1062 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 16/03/2025 to 1900 hrs 16/03/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1106 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 14/03/2025 to 1800 hrs 14/03/2025.
The forecast capacity reserve requirement is 1729 MW.
The minimum capacity reserve available is 1629 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.
The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202503141620_review] Prices for interval 14-Mar-2025 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 14 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.