124289RESERVE NOTICE07/02/2025 04:17:31 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124287 is cancelled at 0415 hrs 07/02/2025.

Manager NEM Real Time Operations
     
124287RESERVE NOTICE07/02/2025 01:44:56 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1700 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1121 MW.


Manager NEM Real Time Operations
     
124281RESERVE NOTICE06/02/2025 09:22:11 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124277 is cancelled at 2120 hrs 06/02/2025.

Manager NEM Real Time Operations
     
124277RESERVE NOTICE06/02/2025 06:00:26 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs 07/02/2025 to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1296 MW.


Manager NEM Real Time Operations
     
124265RESERVE NOTICE06/02/2025 05:19:16 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:


[1.] From 1730 hrs 06/02/2025 to 1800 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1347 MW.


[2.] From 1630 hrs 07/02/2025 to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1248 MW.


Manager NEM Real Time Operations
     
124249RESERVE NOTICE06/02/2025 03:14:14 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 124094 is cancelled at 1400 hrs 06/02/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
124248RESERVE NOTICE06/02/2025 03:13:24 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124184 is cancelled at 1400 hrs 06/02/2025.

No LOR condition is currently forecast in the PDPASA period.

AEMO Operations
     
124233RESERVE NOTICE06/02/2025 08:47:41 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124225 is cancelled at 0840 hrs 06/02/2025.

Manager NEM Real Time Operations
     
124225RESERVE NOTICE05/02/2025 10:32:28 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124191 has been updated to the following:

[1.] From 1600 hrs 06/02/2025 to 1730 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 887 MW.

[2.] From 1930 hrs 06/02/2025 to 2030 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1148 MW.


Manager NEM Real Time Operations
     