Market Notices

110109GENERAL NOTICE03/10/2023 11:26:00 AM

Fast Frequency Response Market Start - 9th October 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO has reviewed the capacity registered and committed for Very Fast FCAS market participation and has determined that both criteria have been met to commence market operations on Monday 9 October 2023 at 1300hrs AEST.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Ben Blake
AEMO Operations
109994GENERAL NOTICE28/09/2023 10:55:03 AM

NEM Local Temperature Alerts for SA from 28 Sep 2023 to 02 Oct 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 2nd Oct

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
109971GENERAL NOTICE26/09/2023 06:28:53 PM

Network Augmentation Commissioned - SA Region - 26/09/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 26/09/2023

Commissioned: Para - Tungkillo No 2 275 kV Line

Manager NEM Real Time Operations
109819GENERAL NOTICE15/09/2023 10:44:14 AM

Network Augmentation Commissioned - SA Region - 15/09/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 15/09/2023

At Cherry Gardens, a new 275 kV Reactor connected to the South 275 kV Bus has been commissioned at 1035 hrs 15/09/2023.

Manager NEM Real Time Operations
109691GENERAL NOTICE07/09/2023 05:27:28 PM

Network Augmentation Commissioned/Decommissioned - SA Region - 07/09/2023

AEMO ELECTRICITY MARKET NOTICE


Network augmentation change in the SA region at 1730 hrs 07/09/2023 as follows:

Commissioned: Tungkillo - Robertstown No.2 275 kV Line

Decommissioned: Para - Robertstown 275 kV Line

Manager NEM Real Time Operations
109633GENERAL NOTICE05/09/2023 09:53:37 AM

QNI minor testing 5th September 2023

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 109448

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Saturday 5th September from 1000 to 1600hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
109603GENERAL NOTICE04/09/2023 07:58:22 PM

Cancellation - Psymetrix PhasorPoint - Unplanned Outage - 04/09/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Psymetrix PhasorPoint - Unplanned Outage - 04/09/2023

Refer AEMO Electricity Market Notice 109602

AEMO Psymetrix PhasorPoint application has returned to service.

Constraint set I-OSC_STAB_MON revoked at 1940 hrs.

Manager NEM Real Time Operations
109602GENERAL NOTICE04/09/2023 06:44:25 PM

Psymetrix PhasorPoint - Unplanned Outage - 04/09/2023

AEMO ELECTRICITY MARKET NOTICE

Psymetrix PhasorPoint - Unplanned Outage - 04/09/2023

There is an unplanned outage of AEMO Psymetrix PhasorPoint application.

Constraint set I-OSC_STAB_MON invoked at 1830hrs 04/09/2023.

This constraint sets contain equations with the following interconnectors on the LHS.

NSW1-QLD1
V-S-MNSP1
V-SA
VIC1-NSW1

Manager NEM Real Time Operations
109448GENERAL NOTICE25/08/2023 05:27:32 PM

QNI Minor testing 26 August 2023

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 109333

There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1200 MW on Saturday 26th August from 0630 to 0900hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake