Update - Non-credible contingency event - Vic region - 09/07/2023
Refer AEMO ELECTRICITY MARKET NOTICE 108846
At 1527 hrs the Mortlake - Blue Gum 500kV Line and Blue Gum to DDWF Line were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - Vic region - 09/07/2023
Non-credible contingency event - Vic region - 09/07/2023
At 0653 hrs the following elements tripped;
- Mortlake PS - Blue Gum 500 kV Line,
- Blue Gum A1 500/220 kV Transformer
- Dundonnell WF tripped.
- MOPS G11 Trans No2 Bus 500 kV CB tripped
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - Vic region - 29/06/2023
Non-credible contingency event - Vic region - 29/06/2023
At 1454 hrs the Altona - Keilor 220 kV line and the Salt Creek windfarm tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: Vic
Duration: 2045 hrs 29/06/2023 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 08/06/2023
Non-credible contingency event - NSW region - 08/06/2023
At 1433 hrs the Liddell - Tomago 330 kV 82 line and Liddell 330 kV CB 5412 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - Vic region - 29/05/2023
Non-credible contingency event - Vic region - 29/05/2023
At 0941hrs the Moorabool No1 220kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - PDPASA - Cancellation of the Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023
The Actual LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 108160 is cancelled at 2045 hrs 25/05/2023.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023
The Actual LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 108160 is cancelled at 2145 hrs 25/05/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 25/05/2023
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 2000 hrs.
The Actual LOR2 condition is forecast to exist until 2030 hrs.
The forecast capacity reserve requirement is 851 MW.
The minimum capacity reserve available is 767 MW.
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement an AEMO intervention event.
Manager NEM Real Time Operations
Non-credible contingency event - Qld region - 23/05/2023
Non-credible contingency event - Qld region - 23/05/2023
At 2106 hrs the Kamerunga - Woree 7141 132 kV Line and Barron Gorge 1 and 2 generating units tripped. At 2107 hrs the Kamerunga - Barron Gorge 7143 132 kV Line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations