Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.
The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024
Manager NEM Real Time Operations
System Reconfiguration - QLD Region - 20/11/2020
System Reconfiguration - QLD Region - 20/11/2020
The following transmission equipment in the Queensland region has been returned to service at 275 kV - 20/11/2020
H13 Ross - H39 Woree No. 8966 275 kV Transmission line - previously operated as 132 kV feeders 7327, 7132 and 7301
The following transmission equipment in the Queensland region has been taken out of service - 20/11/2020
H32 Chalumbin - H39 Woree No. 877 275 kV Transmission line - due to risk of cable failure
The following transmission equipment in the Queensland region has been deenergised - 20/11/2020
H13 Ross - H32 Chalumbin No. 857 275 kV Transmission line - to free up a bay at H13 Ross for the 8966 275 kV line
Manager NEM Real Time Operations
Cancellation of Actual (LOR3) condition in the Vic region - 25/01/2019
Cancellation of Actual (LOR3) condition in the Vic region - 25/01/2019
The Actual LOR3 Condition in the Vic region advised in AEMO Electricity Market Notice No.66768 is cancelled at 1350 hrs 25/01/219.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 25/01/2019
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 25/01/2019
Customer load shedding of non-interruptible load is occurring in the Vic region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the Vic region from 1100 hrs.
The Actual LOR3 condition is forecast to exist until 1500 hrs.
The load interrupted is 100 MW at 1100 hrs 25/01/2019. This may be varied during the actual LOR3 period.
Manager NEM Real Time Operations
Cancellation of Actual (LOR3) condition in the Vic region - 24/01/2019
Cancellation of Actual (LOR3) condition in the Vic region - 24/01/2019
The Actual LOR3 Condition in the Vic region advised in AEMO Electricity Market Notice No.66670 is cancelled at 2000 hrs 24/01/2019.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 24/01/2019
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 24/01/2019
Customer load shedding of non-interruptible load is occurring in the Vic region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the Vic region from 1810 hrs.
The Actual LOR3 condition is forecast to exist until 1910 hrs.
The maximum load to be interrupted is 266MW at 1810 hrs 24/01/2019
Manager NEM Real Time Operations
Cancellation - Actual Lack Of Reserve Level 3 (LOR3) in the NSW Region- 10-02-2017
Cancellation - Actual Lack Of Reserve Level 3 (LOR3) in the NSW Region- 10-02-2017
Refer Electricity Market Notice 57396
Customer load is no longer being interrupted in NSW Region.
The Actual LOR3 condition has been cancelled for the NSW region from 1805 hrs.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the NSW Region- 10-02-2017
Actual Lack Of Reserve Level 3 (LOR3) in the NSW Region- 10-02-2017
Under the NER Cl 4.8.4(d), AEMO considers that Customer load is actually being interrupted in order to maintain or restore the security of the power system in NSW Region.
An Actual LOR3 condition has been declared for the NSW region from 1650 hrs.
The Actual LOR3 condition is forecast to exist until 1800 hrs
The maximum load to be interrupted is 310 MW at 1706 hrs 10/02/2017
Manager NEM Real Time Operations