128160POWER SYSTEM EVENTS18/07/2025 08:49:29 AM

Non-credible contingency event - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 18/07/2025

At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128135RESERVE NOTICE16/07/2025 05:11:13 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1800 hrs 16/07/2025 to 1900 hrs 16/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1343 MW.


Manager NEM Real Time Operations
     
128119RESERVE NOTICE13/07/2025 01:42:17 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.

Manager NEM Real Time Operations
     
128118RESERVE NOTICE13/07/2025 12:51:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.


Manager NEM Real Time Operations
     
128013RESERVE NOTICE08/07/2025 04:46:59 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 08/07/2025 to 1800 hrs 08/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1392 MW.


Manager NEM Real Time Operations
     
127969RESERVE NOTICE06/07/2025 03:07:56 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127957 is cancelled at 1400 hrs 06/07/2025.

Manager NEM Real Time Operations
     
127968RESERVE NOTICE06/07/2025 03:07:26 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127956 is cancelled at 1400 hrs 06/07/2025.

Manager NEM Real Time Operations
     
127957RESERVE NOTICE05/07/2025 02:30:15 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127943 has been updated to the following:

[1.] From 0000 hrs 12/07/2025 to 0330 hrs 12/07/2025.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 366 MW.

Manager NEM Real Time Operations
     
127956RESERVE NOTICE05/07/2025 02:28:42 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127942 has been updated to the following:

[1.] From 0400 hrs 11/07/2025 to 1200 hrs 11/07/2025.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 344 MW.

[2.] From 1630 hrs 11/07/2025 to 0000 hrs 12/07/2025.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 340 MW.

Manager NEM Real Time Operations
     