117210POWER SYSTEM EVENTS27/06/2024 09:01:59 AM

Non-credible contingency event - NSW region - 27/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 27/06/2024

At 0845 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117203RESERVE NOTICE26/06/2024 03:32:26 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0800 hrs to 0900 hrs 03/07/2024.
The forecast capacity reserve requirement is 532 MW.
The minimum capacity reserve available is 505 MW.

2. From 1730 hrs to 2030 hrs 03/07/2024.
The forecast capacity reserve requirement is 526 MW.
The minimum capacity reserve available is 496 MW.

AEMO Operations
     
117202RESERVE NOTICE26/06/2024 03:31:30 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0800 hrs to 0900 hrs 02/07/2024.
The forecast capacity reserve requirement is 536 MW.
The minimum capacity reserve available is 454 MW.

2. From 1730 hrs to 2130 hrs 02/07/2024.
The forecast capacity reserve requirement is 546 MW.
The minimum capacity reserve available is 414 MW.

AEMO Operations
     
117201RESERVE NOTICE26/06/2024 03:30:07 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1800 hrs to 2130 hrs 01/07/2024.
The forecast capacity reserve requirement is 514 MW.
The minimum capacity reserve available is 467 MW.

AEMO Operations
     
117200INTER-REGIONAL TRANSFER26/06/2024 02:36:10 PM

Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/06/2024

A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0815 hrs 26/06/2024 to 1930 hrs 26/06/2024.

The outage has been completed and Heywood - South East No 2 275 kV Line returned to service at 1410 hrs 26/06/2024

Constraint set(s) revoked:
I-HYSE
I-VS_050
I-VS+LKB_050

Manager NEM Real Time Operations
     
117147PRICES UNCHANGED25/06/2024 02:00:54 PM

[EventId:202406251330_confirmed] Prices for interval 25-Jun-2024 13:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1355 hrs on 25 June 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Jun-2024 13:30.

In accordance with Market Notice 117136 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
117146PRICES UNCHANGED25/06/2024 01:59:29 PM

[EventId:202406251355_confirmed] Prices for interval 25-Jun-2024 13:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1355 hrs on 25 June 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Jun-2024 13:55.

In accordance with Market Notice 117141 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
117145PRICES UNCHANGED25/06/2024 01:58:30 PM

[EventId:202406251350_confirmed] Prices for interval 25-Jun-2024 13:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1355 hrs on 25 June 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Jun-2024 13:50.

In accordance with Market Notice 117140 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
117144PRICES UNCHANGED25/06/2024 01:57:28 PM

[EventId:202406251345_confirmed] Prices for interval 25-Jun-2024 13:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1355 hrs on 25 June 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Jun-2024 13:45.

In accordance with Market Notice 117139 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.