117510RESERVE NOTICE30/07/2024 08:43:12 PM

Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117509 is cancelled at 2040 hrs 30/07/2024.

Manager NEM Real Time Operations
     
117509RESERVE NOTICE30/07/2024 08:17:01 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2000 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs

The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 404 MW

Manager NEM Real Time Operations
     
117508GENERAL NOTICE30/07/2024 02:45:25 PM

Increase to QNI limit to next hold point of 1400 MW Qld to NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notices 117060.

AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.

The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
117507MARKET SYSTEMS30/07/2024 01:27:09 PM

CHG0091507 | Production | As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical s

Change Number: CHG0091507

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Business to Business data exchange

Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.

Change Start Date & Time: 26/08/2024 08:00:00 AEST
Change End Date & Time: 28/08/2024 18:00:00 AEST

Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: This is the Inactive Production environment, there is no impact for external participants.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
     
117504RECLASSIFY CONTINGENCY30/07/2024 07:22:04 AM

Update - Non-credible contingency event - QLD region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 30/07/2024

Refer AEMO Electricity Market Notice 117503

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: QLD

Elements: Darling Downs Power Station
Duration: 0720 hrs until further notice
Constraint set(s) invoked: Q-DARLING_DOWNS_N-2

Manager NEM Real Time Operations
     
117503POWER SYSTEM EVENTS30/07/2024 07:07:11 AM

Non-credible contingency event - QLD region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 30/07/2024

At 0537 hrs the Darling Downs Power Station GT1, GT3 and and the steam turbine tripped from 484 MW.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117501RESERVE NOTICE29/07/2024 05:49:35 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region [beginning] on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117497 is cancelled at 0545 hrs 29/07/2024.

Manager NEM Real Time Operations
     
117500POWER SYSTEM EVENTS28/07/2024 05:14:14 PM

Update - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 27/07/2024

Refer AEMO Electricity Market Notice 117487

At 1702 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
117499RESERVE NOTICE28/07/2024 02:51:28 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117493 is cancelled at 1420 hrs 28/07/2024

No LOR condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm