Filter by category
Filter by Date
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1549 MW
The minimum capacity reserve available is 1164 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 09/04/2025 to 1800 hrs 09/04/2025.
The forecast capacity reserve requirement is 1519 MW.
The minimum capacity reserve available is 1500 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025.
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126441 is cancelled at 1440 hrs 09/04/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 10/04/2025 to 1830 hrs 10/04/2025.
The forecast capacity reserve requirement is 1581 MW.
The minimum capacity reserve available is 1580 MW.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 04/04/2025
Update - Non-credible contingency event - QLD region - 04/04/2025
Refer AEMO Electricity Market Notice 126262
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will cancel the reclassification of this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 04/04/2025
Non-credible contingency event - QLD region - 04/04/2025
At 0152 hrs the Ross - Townsville South No 7156 and 7249 132kV lines tripped and auto reclosed.
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: QLD
Elements: Ross - Townsville South No 7156 and 7249 132kV lines.
Duration: 0152 hrs 04/04/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 26/03/2025
Non-credible contingency event - TAS region - 26/03/2025
At 1551 hrs the Palmerston A 220kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
Approximately 40MW of generation was disconnected.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025
Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125715 is cancelled at 1915 hrs 16/03/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The forecast capacity reserve requirement is 1684 MW.
The minimum capacity reserve available is 1242 MW.
Manager NEM Real Time Operations