Market Notices

117569MARKET INTERVENTION06/08/2024 04:59:17 PM

Direction - SA region 06/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 06/08/2024

Refer to Market Notice 117568


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1700 hrs 06/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1030 hrs 07/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 07/08/2024

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
117568MARKET INTERVENTION06/08/2024 02:24:15 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 117566

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 07/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 06/08/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
117566MARKET INTERVENTION06/08/2024 12:57:46 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 07/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
117565RESERVE NOTICE05/08/2024 09:47:16 PM

Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117564 is cancelled at 2145 hrs 05/08/2024.

Manager NEM Real Time Operations
     
117564RESERVE NOTICE05/08/2024 09:25:40 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

The actual LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117563 has been updated at 2120 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2130 hrs.

The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 377 MW.

Manager NEM Real Time Operations
     
117563RESERVE NOTICE05/08/2024 08:44:48 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs.

The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 428 MW

Manager NEM Real Time Operations
     
117545NON-CONFORMANCE04/08/2024 06:30:18 AM

NON-CONFORMANCE Region QLD1 Sunday, 4 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 4 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: W/HOE#2
Duration: 04/08/2024 06:25 to 04/08/2024 06:30
Amount: -165 MW
Constraint: NC-Q_W/HOE#2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117542NON-CONFORMANCE03/08/2024 04:35:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 3 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 3 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW03
Duration: 03/08/2024 16:25 to 03/08/2024 16:35
Amount: 72 MW
Constraint: NC-N_BW03

Auto-generated on behalf of Manager NEM Real Time Operations
     
117539NON-CONFORMANCE02/08/2024 06:15:12 PM

NON-CONFORMANCE Region SA1 Friday, 2 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 2 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 02/08/2024 12:10 to 02/08/2024 18:15
Amount: 14 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     