117149RECLASSIFY CONTINGENCY25/06/2024 03:09:51 PM

Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Duration: 25/06/2024 15:09 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
117148RECLASSIFY CONTINGENCY25/06/2024 03:09:51 PM

Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Duration: 25/06/2024 15:09 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
117141PRICES SUBJECT TO REVIEW25/06/2024 01:50:19 PM

[EventId:202406251355_review] Prices for interval 25-Jun-2024 13:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1350 hrs on 25 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117140PRICES SUBJECT TO REVIEW25/06/2024 01:45:18 PM

[EventId:202406251350_review] Prices for interval 25-Jun-2024 13:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1345 hrs on 25 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117139PRICES SUBJECT TO REVIEW25/06/2024 01:43:30 PM

[EventId:202406251345_review] Prices for interval 25-Jun-2024 13:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117138PRICES SUBJECT TO REVIEW25/06/2024 01:42:34 PM

[EventId:202406251340_review] Prices for interval 25-Jun-2024 13:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117137PRICES SUBJECT TO REVIEW25/06/2024 01:40:05 PM

[EventId:202406251335_review] Prices for interval 25-Jun-2024 13:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117136PRICES SUBJECT TO REVIEW25/06/2024 01:41:22 PM

[EventId:202406251330_review] Prices for interval 25-Jun-2024 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117133INTER-REGIONAL TRANSFER25/06/2024 10:28:52 AM

Inter-regional transfer limit variation -Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024

A planned outage of Hazelwood - South Morang No 1 500 kV Line in the VIC region was scheduled from 0800 hrs 25/06/2024 to 1530 hrs 25/06/2024.

The outage has been completed and Hazelwood - South Morang No 1 500 kV Line returned to service at 1016 hrs 25/06/2024

Constraint set(s) revoked: V-HWSM

Manager NEM Real Time Operations
     