Market Notices

117823PRICES SUBJECT TO REVIEW27/08/2024 10:10:20 AM

[EventId:202408271015_review] Prices for interval 27-Aug-2024 10:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117822PRICES SUBJECT TO REVIEW27/08/2024 10:05:26 AM

[EventId:202408271010_review] Prices for interval 27-Aug-2024 10:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117821PRICES SUBJECT TO REVIEW27/08/2024 10:00:18 AM

[EventId:202408271005_review] Prices for interval 27-Aug-2024 10:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117820PRICES SUBJECT TO REVIEW27/08/2024 09:55:25 AM

[EventId:202408271000_review] Prices for interval 27-Aug-2024 10:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0955 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117819PRICES SUBJECT TO REVIEW27/08/2024 09:50:20 AM

[EventId:202408270955_review] Prices for interval 27-Aug-2024 09:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0950 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 09:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117818RECLASSIFY CONTINGENCY27/08/2024 05:36:33 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 0530 hrs 27 Aug 2024 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
117817RECLASSIFY CONTINGENCY26/08/2024 01:57:09 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Sydney West No.1 330 kV SVC and any single Sydney West 330/132 kV transformer

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a Non-Credible Contingency Event: Sydney West No.1 330 kV SVC and any single Sydney West 330/132 kV transformer
Refer AEMO Electricity Market Notice 117212

AEMO considers the simultaneous trip of the following elements no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW

Elements: Sydney West No.1 330 kV SVC and any single Sydney West 330/132 kV transformer
Cancellation time:: 1400 hrs 26/08/2024
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
117809MARKET SYSTEMS26/08/2024 09:49:57 AM

CHG0095221 | Cancelled | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0095221
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal

Service/ Component: Gas Hub

Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     
117808MARKET SYSTEMS26/08/2024 09:47:55 AM

CHG0091459 | Cancelled | Production | MSATS CATS & URM Site Transfer BNE to NOR Data Centre

Change Number: CHG0091459
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: MSATS CATS & URM Site Transfer BNE to NOR Data Centre

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm