117669INTER-REGIONAL TRANSFER14/08/2024 08:05:49 AM

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

A planned outage of Collector - Marulan No 4 330kV Line in the NSW region was scheduled from 0800 hrs 14/08/2024 to 1700 hrs 02/09/2024.


The outage has been cancelled.

Constraint set(s) invoked: N-CTMN_4_WG_CLOSE


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117650GENERAL NOTICE12/08/2024 09:31:53 AM

QNI Minor testing (NSW to Qld) 12th August 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 116052

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Monday 12th August 2024 from 1100 to 1700hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
117617PRICES SUBJECT TO REVIEW09/08/2024 07:55:10 PM

[EventId:202408092000_review] Prices for interval 09-Aug-2024 20:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1955 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 20:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117616PRICES SUBJECT TO REVIEW09/08/2024 07:50:19 PM

[EventId:202408091955_review] Prices for interval 09-Aug-2024 19:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1950 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 19:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117615PRICES SUBJECT TO REVIEW09/08/2024 07:45:18 PM

[EventId:202408091950_review] Prices for interval 09-Aug-2024 19:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1945 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 19:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117614PRICES SUBJECT TO REVIEW09/08/2024 07:40:18 PM

[EventId:202408091945_review] Prices for interval 09-Aug-2024 19:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1940 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 19:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117613PRICES SUBJECT TO REVIEW09/08/2024 07:35:18 PM

[EventId:202408091940_review] Prices for interval 09-Aug-2024 19:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1935 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 19:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117612PRICES SUBJECT TO REVIEW09/08/2024 07:30:12 PM

[EventId:202408091935_review] Prices for interval 09-Aug-2024 19:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 19:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117601PRICES SUBJECT TO REVIEW09/08/2024 07:55:20 AM

[EventId:202408090800_review] Prices for interval 09-Aug-2024 08:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 08:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     