Market Notices

128346SETTLEMENTS RESIDUE25/07/2025 06:30:26 PM

[EventId:202507251830_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 25 July 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 25 July 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2025.

Refer to market notice: 128338

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1830 hrs on 25 July 2025.

This is an AEMO autogenerated Market Notice.
     
128345RECLASSIFY CONTINGENCY25/07/2025 06:05:20 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 1800 hrs 25/07/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 128304

Manager NEM Real Time Operations
     
128338SETTLEMENTS RESIDUE25/07/2025 05:35:24 PM

[EventId:202507251735_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 25 July 2025 17:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 25 July 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1735 hrs on 25 July 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
128337SETTLEMENTS RESIDUE25/07/2025 05:35:24 PM

[EventId:202507251735_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 25 July 2025 17:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 25 July 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 25 July 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1735 hrs on 25 July 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
128318MARKET INTERVENTION25/07/2025 05:00:06 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 128311

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/07/2025.

The direction update is issued at 1700 hrs 25/07/2025.

Manager NEM Real Time Operations
     
128317RESERVE NOTICE25/07/2025 03:07:49 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 28/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128313 is cancelled at 1400 hrs 25/07/2025.

No LOR condition is currently forecast in the STPASA period.


AEMO Operations
     
128315RECLASSIFY CONTINGENCY25/07/2025 01:31:20 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 128312 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 1330 hrs 25/07/2025

Constraint set(s) revoked: I-VS_250

Manager NEM Real Time Operations
     
128314MARKET INTERVENTION25/07/2025 12:36:03 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0400 hrs 26/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
128313RESERVE NOTICE25/07/2025 10:27:08 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 28/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0730 hrs to 0900 hrs 28/07/2025.
The forecast capacity reserve requirement is 563 MW.
The minimum capacity reserve available is 536 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.