Filter by category
Filter by Date
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 3 Leg of Directlink .
The following constraint set was invoked at 2255 hrs 12/07/2025
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Braemar (R2) No.1 330/275 kV Transformer - QLD region - 12/07/2025
Inter-regional transfer limit variation - Braemar (R2) No.1 330/275 kV Transformer - QLD region - 12/07/2025
At 2145 hrs 12/07/2025 there was an unplanned outage of Braemar (R2) No.1 330/275 kV Transformer.
The following constraint set(s) invoked at 2145 hrs 12/07/2025
Q-BRTX1
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1350 hrs 12/07/2025
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Completed - CHG0104394 - Planned maintenance affecting the AEMO Market Network.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Completed - CHG0104582 - Pre-Prod eMDM Maintenance Release
Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202507092030_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 July 2025 20:30
Issued by Australian Energy Market Operator Ltd at 2030 hrs on 9 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Refer to market notice: 128067
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 2030 hrs on 9 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507091905_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 09 July 2025 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 9 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1905 hrs on 9 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202507091830_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 July 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 9 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Refer to market notice: 128065
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1830 hrs on 9 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507091735_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 09 July 2025 17:35
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 9 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1735 hrs on 9 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.