126783INTER-REGIONAL TRANSFER29/04/2025 04:51:17 PM

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line- NSW region - 29/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line - NSW region - 29/04/2025

A planned outage of Eraring - Kemps Creek 5A1 500 kV line in the NSW region was scheduled from 0730 hrs 28/04/2025 to 1600 hrs 02/05/2025.

The outage has been completed and Eraring - Kemps Creek 5A1 500 kV line returned to service at 1650 hrs 29/04/2025

Constraint set revoked: N-ERKC_ONE

Manager NEM Real Time Operations
     
126762PRICES SUBJECT TO REVIEW27/04/2025 02:50:26 PM

[EventId:202504271455_review] Prices for interval 27-Apr-2025 14:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126759PRICES SUBJECT TO REVIEW27/04/2025 02:45:15 PM

[EventId:202504271450_review] Prices for interval 27-Apr-2025 14:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126758PRICES SUBJECT TO REVIEW27/04/2025 02:40:13 PM

[EventId:202504271445_review] Prices for interval 27-Apr-2025 14:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126757PRICES SUBJECT TO REVIEW27/04/2025 02:35:22 PM

[EventId:202504271440_review] Prices for interval 27-Apr-2025 14:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126756PRICES SUBJECT TO REVIEW27/04/2025 02:30:11 PM

[EventId:202504271435_review] Prices for interval 27-Apr-2025 14:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126755PRICES SUBJECT TO REVIEW27/04/2025 02:25:10 PM

[EventId:202504271430_review] Prices for interval 27-Apr-2025 14:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1425 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126754PRICES SUBJECT TO REVIEW27/04/2025 02:20:17 PM

[EventId:202504271425_review] Prices for interval 27-Apr-2025 14:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126740INTER-REGIONAL TRANSFER26/04/2025 11:57:04 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025

At 1140 hrs 26/04/2025 there was a short notice outage of Griffith - Yanco 99J 132 kV Line.

The following constraint set(s) invoked at 1140 hrs 26/04/2025
N-GFYC-99J-C

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.