Planned outage of Dapto - Kangaroo Valley (18) 330 kV line in the NSW region on 20/07/2025
The Dapto - Kangaroo Valley (18) 330 kV line in the New South Wales (NSW) region is planned to be out of service from 0615 hrs to 1630 hrs 20/07/2025.
This outage is considered as a High Impact Outage (HIO).
During this planned outage:
- There is a potential for Energy and FCAS prices to approach the Market Price Cap.
- Power transfer will be restricted between VIC/Snowy and NSW.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
Non-credible contingency event - QLD region - 18/07/2025
Non-credible contingency event - QLD region - 18/07/2025
At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 16/07/2025 to 1900 hrs 16/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1343 MW.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 14/07/2025
Network Augmentation Commissioned - NSW Region - 14/07/2025
Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.
Manager NEM Real Time Operations
[EventId:202507092030_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 July 2025 20:30
Issued by Australian Energy Market Operator Ltd at 2030 hrs on 9 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Refer to market notice: 128067
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 2030 hrs on 9 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507091905_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 09 July 2025 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 9 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1905 hrs on 9 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202507091830_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 July 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 9 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Refer to market notice: 128065
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1830 hrs on 9 July 2025.