Filter by category
Filter by Date
[EventId:202507212000_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 21 July 2025 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 21 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 21 July 2025.
Refer to market notice: 128216
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2000 hrs on 21 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507211900_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 21 July 2025 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 21 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 21 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1900 hrs on 21 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region SA1 Monday, 21 July 2025
NON-CONFORMANCE SA1 Region Monday, 21 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 21/07/2025 18:40 to 21/07/2025 18:45
Amount: 11 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202507211830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 July 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 21 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 July 2025.
Refer to market notice: 128212
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 21 July 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202507211630_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 July 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 21 July 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 July 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1630 hrs on 21 July 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Sunday, 20 July 2025
NON-CONFORMANCE QLD1 Region Sunday, 20 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 20/07/2025 15:45 to 20/07/2025 15:55
Amount: -51 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Eraring 500kV - Kemps Creek 5A2 500kV Line - NSW region - 19/07/2025
Inter-regional transfer limit variation - Eraring500kV - Kemps Creek 5A2 500kV Line - NSW region - 19/07/2025
At 1910 hrs 19/07/2025 there was a short notice outage of Eraring 500kV - Kemps Creek 5A2 500kV Line .
The following constraint set(s) invoked at 1920 hrs 19/07/2025
N-ERKC_ONE
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Bulgana-Horsham 220kV LINE - VIC region - 19/07/2025
Inter-regional transfer limit variation - Bulgana-Horsham 220kV LINE - VIC region - 19/07/2025
A planned outage of Bulgana-Horsham 220kV LINE in the VIC region was scheduled from 0700 hrs 19/07/2025 to 1730 hrs 19/07/2025.
The outage has been completed and Bulgana-Horsham 220kV LINE returned to service at 1525 hrs 19/07/2025
Constraint set(s) revoked: V-BUHO
Manager NEM Real Time Operations
Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025
Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025
At 1207 hrs 18/07/2025 there was an unplanned outage of S3 Greenbank 275 kV SVC.
The following constraint set(s) invoked at 1215 hrs 18/07/2025
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations