Market Notices

Notice type *
MARKET SUSPENSION

Notice type description *
Market suspended in region(s).

External reference *
Declaration of electricity market suspension

Reason *
AEMO ELECTRICITY MARKET NOTICE

Declaration of electricity market suspension

AEMO declares the spot market suspended in the NEM with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1400 hrs on 05 September 2024 until further notice. Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.

There has been a failure of the NEM dispatch process, and all participants to follow existing targets until further notice.

Manager NEM Real Time Operations

113687RESERVE NOTICE24/01/2024 08:45:26 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113684 is cancelled at 0800 hrs 24/01/2024.

AEMO Operations
113686RESERVE NOTICE24/01/2024 08:43:27 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113680 has been updated at 0800 hrs 24/01/2024 to the following:

From 1700 hrs to 2030 hrs 27/01/2024.
The forecast capacity reserve requirement is 716 MW.
The minimum capacity reserve available is 361 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113685RESERVE NOTICE24/01/2024 08:42:39 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113679 has been updated at 0800 hrs 24/01/2024 to the following:

From 1730 hrs to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1343 MW.
The minimum capacity reserve available is 1087 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113684RESERVE NOTICE24/01/2024 05:32:57 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113678 has been updated at 0530 hrs 24/01/2024 to the following:

[1.] From 1530 hrs 25/01/2024 to 1600 hrs 25/01/2024.
The forecast capacity reserve requirement is 1133 MW.
The minimum capacity reserve available is 1087 MW.

[2.] From 1630 hrs 25/01/2024 to 1800 hrs 25/01/2024.
The forecast capacity reserve requirement is 1141 MW.
The minimum capacity reserve available is 990 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113682RESERVE NOTICE24/01/2024 04:36:02 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113681 has been updated at 0430 hrs 24/01/2024 to the following:

1.] From 1800 hrs 26/01/2024 to 2000 hrs 26/01/2024.
The forecast capacity reserve requirement is 729 MW.
The minimum capacity reserve available is 543 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113681RESERVE NOTICE24/01/2024 12:00:33 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113677 has been updated at 2330 hrs 23/01/2024 to the following:

[1.] From 1700 hrs 26/01/2024 to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 798 MW.
The minimum capacity reserve available is 502 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113680RESERVE NOTICE23/01/2024 11:59:25 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1730 hrs 27/01/2024 to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 725 MW.
The minimum capacity reserve available is 600 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113679RESERVE NOTICE23/01/2024 11:41:35 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113676 has been updated at 2330 hrs 23/01/2024 to the following:

[1.] From 1700 hrs 26/01/2024 to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1278 MW.
The minimum capacity reserve available is 730 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113678RESERVE NOTICE23/01/2024 11:40:29 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113675 has been updated at 2330 hrs 23/01/2024 to the following:

[1.] From 1630 hrs 25/01/2024 to 1700 hrs 25/01/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 1021 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm