114648MARKET INTERVENTION13/02/2024 05:21:13 PM

Possible intervention to manage power system security in VIC region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in VIC region

The synchronous generating units currently expected to be synchronised in VIC from 1830 hrs 13/02/2024 will be inadequate to maintain a secure operating state in VIC .

AEMO estimates that, in the absence of sufficient market response by 1730 hrs 13/02/2024, AEMO may need to intervene by issuing a direction requiring one or more VIC synchronous generating unit(s) to operate or remain synchronised to maintain power system security in VIC.

Manager NEM Real Time Operations
114646SETTLEMENTS RESIDUE13/02/2024 04:30:20 PM

[EventId:202402131630_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 13 February 2024 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 13 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 February 2024.

Refer to market notice: 114616

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1630 hrs on 13 February 2024.

This is an AEMO autogenerated Market Notice.
114645SETTLEMENTS RESIDUE13/02/2024 04:31:23 PM

[EventId:202402131630_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 13 February 2024 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 13 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 13 February 2024.

Refer to market notice: 114615

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1630 hrs on 13 February 2024.

This is an AEMO autogenerated Market Notice.
114632RESERVE NOTICE13/02/2024 03:19:41 PM

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.

Manager NEM Real Time Operations
114616SETTLEMENTS RESIDUE13/02/2024 02:52:18 PM

[EventId:202402131450_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 13 February 2024 14:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 13 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1450 hrs on 13 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114615SETTLEMENTS RESIDUE13/02/2024 02:51:16 PM

[EventId:202402131450_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 13 February 2024 14:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 13 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 13 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1450 hrs on 13 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114604RESERVE NOTICE13/02/2024 02:27:41 PM

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.

An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.

The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024

Manager NEM Real Time Operations
114603MARKET INTERVENTION13/02/2024 02:18:14 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
114602MARKET INTERVENTION13/02/2024 02:18:13 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations