CHG0082301 | Production | Planned System Maintenance - Electricity MMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - Electricity MMS Production Bay transfer
Change Start Date & Time: 11/12/2023 13:00:00 AEST
Change End Date & Time: 13/12/2023 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The maintenance activity is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600 .
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112179 is cancelled at 1400 hrs 11/12/2023.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
CHG0081726 | Completed | Production | Renewal of webMethods ESB server certificate
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Renewal of webMethods ESB server certificate
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082105 | Completed | Production | BAU Retail Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: BAU Retail Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Non-credible contingency event - SA region - 11/12/2023
Non-credible contingency event - SA region - 11/12/2023
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112125 is cancelled at 0945 hrs 09/12/2023.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112119 has been updated at 0515 hrs 09/12/2023 to the following:
From 1700 hrs 09/12/2023 to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 704 MW.
The minimum capacity reserve available is 625 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1130 hrs on 09/12/2023.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112081 has been updated at 1715 hrs 08/12/2023 to the following:
From 1600 hrs 09/12/2023 to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 987 MW.
The minimum capacity reserve available is 761 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1130 hrs on 09/12/2023.
Manager NEM Real Time Operations