Market Notices

113841MARKET INTERVENTION27/01/2024 11:49:38 AM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - QLD1 Region- 27/01/2024

Refer to AEMO Electricity Market Notice no. 113840.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
17:30 to 21:00 hrs 27/01/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
113839MARKET INTERVENTION27/01/2024 12:33:35 PM

Direction - QLD region 27/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - QLD region 27/01/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the QLD region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a reliable operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1235 hrs on 27/01/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
113832SETTLEMENTS RESIDUE27/01/2024 10:30:25 AM

[EventId:202401271030_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 January 2024 10:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 27 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1030 hrs on 27 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113825POWER SYSTEM EVENTS27/01/2024 01:57:16 AM

Non-credible contingency event - QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/01/2024

At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
113822SETTLEMENTS RESIDUE26/01/2024 08:31:27 PM

[EventId:202401262030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 January 2024 20:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2030 hrs on 26 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 January 2024.

Refer to market notice: 113818

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2030 hrs on 26 January 2024.

This is an AEMO autogenerated Market Notice.
113821SETTLEMENTS RESIDUE26/01/2024 08:30:22 PM

[EventId:202401262030_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 26 January 2024 20:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2030 hrs on 26 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 26 January 2024.

Refer to market notice: 113805

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2030 hrs on 26 January 2024.

This is an AEMO autogenerated Market Notice.
113818SETTLEMENTS RESIDUE26/01/2024 07:11:49 PM

[EventId:202401261905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 January 2024 19:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 26 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1905 hrs on 26 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113805SETTLEMENTS RESIDUE26/01/2024 06:30:29 PM

[EventId:202401261830_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 26 January 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 26 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 26 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1830 hrs on 26 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113803MARKET INTERVENTION26/01/2024 04:47:43 PM

Update - Direction - SA Region - 24/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 24/01/2024

Refer Market Notice 113710

The AEMO intervention event that commenced from interval ending 1635 hrs on 24/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm