Market Notices

63100RESERVE NOTICE06/06/2018 05:12:04 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/06/2018

AEMO ELECTRICITY MARKET NOTICE

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs 06/06/2018

The Actual LOR1 condition is forecast to exist until 1900 hrs 06/06/2018.

The capacity reserve requirement is 1550 MW.
The capacity reserve available is 1349 MW.

Manager NEM Real Time Operations


63089RESERVE NOTICE05/06/2018 07:20:16 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/06/2018

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/06/2018
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.63067 is cancelled at 1915 hrs 05/06/2018.

Manager NEM Real Time Operations
63087RESERVE NOTICE05/06/2018 06:41:42 PM

Cancellation of Actual (LOR1) condition in the QLD region - 05/06/2018

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No. 63086 is cancelled at 1830 hrs.

Manager NEM Real Time Operations
63086RESERVE NOTICE05/06/2018 06:34:56 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2018


AEMO ELECTRICITY MARKET NOTICE

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs 05/06/2018

The Actual LOR1 condition is forecast to exist until 1830 hrs 05/06/2018.

The capacity reserve requirement is 850 MW.
The capacity reserve available is 795 MW.

Manager NEM Real Time Operations

63067RESERVE NOTICE05/06/2018 04:26:17 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/06/2018

AEMO ELECTRICITY MARKET NOTICE

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600hrs 05/06/2018
The Actual LOR1 condition is forecast to exist until 1830 hrs 05/06/2018.
The capacity reserve requirement is 1560 MW.
The capacity reserve available is 1305 MW.

Manager NEM Real Time Operations

63064RESERVE NOTICE04/06/2018 11:55:10 PM

Cancellation of Actual (LOR1) condition in the NSW region - 5/06/2018

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 63063 is cancelled at 2330 hrs 4/06/2018.

Manager NEM Real Time Operations
63062RESERVE NOTICE04/06/2018 07:15:40 PM

Cancellation of Actual (LOR1) condition in the NSW region - 4/06/2018

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 63061 is cancelled at 1900 hrs 4/06/2018.

Manager NEM Real Time Operations
63061RESERVE NOTICE04/06/2018 05:34:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/06/2018

AEMO ELECTRICITY MARKET NOTICE
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs 04/06/2018
The Actual LOR1 condition is forecast to exist until 1900 hrs 04/06/2018.
The capacity reserve requirement is 1560 MW.
The capacity reserve available is 1339 MW.
Manager NEM Real Time Operations
63024CONSTRAINTS30/05/2018 03:07:18 PM

Updated generator combination for SA system strength

AEMO MARKET NOTICE

Updated generator combination for SA system strength

AEMO is continuing to investigate system strength requirements in South Australia.

Through this work, AEMO has identified an additional generator combination which meets minimum system strength requirements in South Australia.

The new combination is:
LOW_35 - 1 x Torrens Island A unit + 1 x Pelican Point GT/ST units + Osborne GT & ST + Mintaro

For more information refer to the updated limits advice:
https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Congestion-Information/2018/Transfer-Limit-Advice---South-Australian-System-Strength.pdf

A further update to this advice is planned before the end of June 2018.