Market Notices

112893INTER-REGIONAL TRANSFER29/12/2023 05:27:51 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 29/12/2023

In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYDS_549FBEF5 from 1650 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Manager NEM Real Time Operations
112870PRICES SUBJECT TO REVIEW29/12/2023 12:05:18 PM

[EventId:202312291210_review] Prices for interval 29-Dec-2023 12:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1205 hrs on 29 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Dec-2023 12:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112868PRICES SUBJECT TO REVIEW29/12/2023 12:00:24 PM

[EventId:202312291205_review] Prices for interval 29-Dec-2023 12:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 29 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Dec-2023 12:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112867PRICES SUBJECT TO REVIEW29/12/2023 11:55:23 AM

[EventId:202312291200_review] Prices for interval 29-Dec-2023 12:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1155 hrs on 29 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Dec-2023 12:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112866PRICES SUBJECT TO REVIEW29/12/2023 11:50:22 AM

[EventId:202312291155_review] Prices for interval 29-Dec-2023 11:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1150 hrs on 29 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Dec-2023 11:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112865PRICES SUBJECT TO REVIEW29/12/2023 11:45:23 AM

[EventId:202312291150_review] Prices for interval 29-Dec-2023 11:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 29 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Dec-2023 11:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112864PRICES SUBJECT TO REVIEW29/12/2023 11:40:18 AM

[EventId:202312291145_review] Prices for interval 29-Dec-2023 11:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1140 hrs on 29 December 2023

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Dec-2023 11:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
112860INTER-REGIONAL TRANSFER29/12/2023 04:03:53 AM

Inter-regional transfer limit variation - Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023

At 0355 hrs 29/12/2023 there was a short notice outage of Para No.1 and No.2 275 kV SVC.

The following constraint set(s) invoked at 0355 hrs 29/12/2023
S-X_PA_VC_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112859INTER-REGIONAL TRANSFER29/12/2023 01:58:35 AM

Inter-regional transfer limit variation - Para No.1 275 kV SVC - SA region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Para No.1 275 kV SV - SA region - 29/12/2023

At 0145 hrs 29/12/2023 there was a short notice outage of Para No.1 275 kV SVC.

The following constraint set(s) invoked at 0145 hrs 29/12/2023
S-PA_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations