114656MARKET INTERVENTION13/02/2024 05:38:24 PM

Direction - VIC region 13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - VIC region 13/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the VIC region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1735 hrs on 13/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
114648MARKET INTERVENTION13/02/2024 05:21:13 PM

Possible intervention to manage power system security in VIC region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in VIC region

The synchronous generating units currently expected to be synchronised in VIC from 1830 hrs 13/02/2024 will be inadequate to maintain a secure operating state in VIC .

AEMO estimates that, in the absence of sufficient market response by 1730 hrs 13/02/2024, AEMO may need to intervene by issuing a direction requiring one or more VIC synchronous generating unit(s) to operate or remain synchronised to maintain power system security in VIC.

Manager NEM Real Time Operations
114632RESERVE NOTICE13/02/2024 03:19:41 PM

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.

Manager NEM Real Time Operations
114604RESERVE NOTICE13/02/2024 02:27:41 PM

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.

An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.

The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024

Manager NEM Real Time Operations
114603MARKET INTERVENTION13/02/2024 02:18:14 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
114602MARKET INTERVENTION13/02/2024 02:18:13 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
114561GENERAL NOTICE13/02/2024 12:03:06 PM

Variation to FCAS regulation raise requirements: NEM Mainland - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Variation to FCAS regulation raise requirements: NEM Mainland - 13/02/2024

FCAS Raise regulation requirements have been increased.to manage frequency.

The following constraint set has been invoked.

F-MAIN_RREG_0450 at 1200 hrs.


Manager NEM Real Time Operations
114536MARKET INTERVENTION12/02/2024 05:04:50 PM

Direction - SA region 12/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 12/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 12/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
114530MARKET INTERVENTION12/02/2024 02:39:15 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 114527

The synchronous generating units currently expected to be synchronised in SA from 0700 hrs 13/02/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 12/02/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.