Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/07/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/07/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1025 MW
Manager NEM Real Time Operations
[EventId:202507131030_review] Prices for interval 13-Jul-2025 10:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1025 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131025_review] Prices for interval 13-Jul-2025 10:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131020_review] Prices for interval 13-Jul-2025 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131015_review] Prices for interval 13-Jul-2025 10:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131010_review] Prices for interval 13-Jul-2025 10:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1005 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507131005_review] Prices for interval 13-Jul-2025 10:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 13 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Jul-2025 10:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 3 Leg of Directlink .
The following constraint set was invoked at 2255 hrs 12/07/2025
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Braemar (R2) No.1 330/275 kV Transformer - QLD region - 12/07/2025
Inter-regional transfer limit variation - Braemar (R2) No.1 330/275 kV Transformer - QLD region - 12/07/2025
At 2145 hrs 12/07/2025 there was an unplanned outage of Braemar (R2) No.1 330/275 kV Transformer.
The following constraint set(s) invoked at 2145 hrs 12/07/2025
Q-BRTX1
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations