113095INTER-REGIONAL TRANSFER07/01/2024 01:32:17 PM

Inter-regional transfer limit variation - Crowlands-Bulgana-Horsham 220 kV Line - Vic region - 07/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Crowlands-Bulgana-Horsham 220 kV Line - Vic region - 07/01/2024

At 1152 hrs 07/01/2024 there was an unplanned outage of the Crowlands-Bulgana-Horsham 220 kV Line.

The following constraint set invoked at 12:05 hrs 07/01/2024
V-CWHO

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
V-SA
VIC1-NSW1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113082RESERVE NOTICE06/01/2024 02:45:06 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113066 has been updated at 1400 hrs 06/01/2024 to the following:

1. From 1730 hrs 10/01/2024 to 1800 hrs 10/01/2024.
The forecast capacity reserve requirement is 1655 MW.
The minimum capacity reserve available is 1565 MW.

Manager NEM Real Time Operations
113081RESERVE NOTICE06/01/2024 02:44:00 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113065 has been updated at 1400 hrs 06/01/2024 to the following:

1. From 1500 hrs 09/01/2024 to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1142 MW.

Manager NEM Real Time Operations
113066RESERVE NOTICE05/01/2024 02:57:09 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1800 hrs 10/01/2024.
The forecast capacity reserve requirement is 1568 MW.
The minimum capacity reserve available is 1560 MW.

AEMO Operations
113065RESERVE NOTICE05/01/2024 02:56:13 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113051 has been updated at 1400 hrs 05/01/2024 to the following:

1. From 1400 hrs to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 721 MW.

2. From 1630 hrs to 1800 hrs 09/01/2024.
The forecast capacity reserve requirement is 1612 MW.
The minimum capacity reserve available is 1258 MW.

AEMO Operations
113051RESERVE NOTICE04/01/2024 03:05:46 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1119 MW.

AEMO Operations
113013INTER-REGIONAL TRANSFER03/01/2024 12:32:13 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 03/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 03/01/2024

At 1220 hrs 03/01/2024 there was an unplanned outage of the South Pine SVC.

The following constraint set(s) invoked at 1230 hrs 03/01/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113008INTER-REGIONAL TRANSFER03/01/2024 09:56:40 AM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 113007

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 0940 hrs.

Manager NEM Real Time Operations
113007INTER-REGIONAL TRANSFER03/01/2024 09:25:47 AM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 0920 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations