Non-credible contingency event - QLD region - 23/01/2024
Non-credible contingency event - QLD region - 23/01/2024
At 0957 hrs the Strathmore No 2 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
The following constraint set(s) invoked
Q-NESTM
Q-X_NQ_275_FDR+BUS
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.
The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 22 January 2024
NON-CONFORMANCE VIC1 Region Monday, 22 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS4
Duration: 22/01/2024 04:15 to 22/01/2024 05:10
Amount: 27 MW
Constraint: NC-V_YWPS4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 21 January 2024
NON-CONFORMANCE QLD1 Region Sunday, 21 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 21/01/2024 17:20 to 21/01/2024 17:35
Amount: 34 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 20 January 2024
NON-CONFORMANCE SA1 Region Saturday, 20 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LKBONNY1
Duration: 20/01/2024 12:10 to 20/01/2024 12:15
Amount: 18 MW
Constraint: NC-S_LKBONNY1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 19 January 2024
NON-CONFORMANCE NSW1 Region Friday, 19 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MP2
Duration: 19/01/2024 07:00 to 19/01/2024 07:05
Amount: 16 MW
Constraint: NC-N_MP2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 18 January 2024
NON-CONFORMANCE NSW1 Region Thursday, 18 January 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 18/01/2024 14:50 to 18/01/2024 15:20
Amount: 19 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 3 Leg of Directlink .
The following constraint set was invoked at 1510 hrs 18/01/2024
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 18 January 2024
NON-CONFORMANCE QLD1 Region Thursday, 18 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 18/01/2024 08:45 to 18/01/2024 09:25
Amount: -41 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations