Market Notices

118187PRICES SUBJECT TO REVIEW08/09/2024 06:15:12 PM

[EventId:202409081820_review] Prices for interval 08-Sep-2024 18:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 8 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118186PRICES SUBJECT TO REVIEW08/09/2024 06:10:49 PM

[EventId:202409081815_review] Prices for interval 08-Sep-2024 18:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1810 hrs on 8 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118184PRICES SUBJECT TO REVIEW08/09/2024 06:05:24 PM

[EventId:202409081810_review] Prices for interval 08-Sep-2024 18:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 8 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118183MARKET INTERVENTION08/09/2024 04:02:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118174

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 09/09/2024.

The direction update is issued at 1600 hrs 08/09/2024.

Manager NEM Real Time Operations
     
118182MARKET INTERVENTION08/09/2024 04:01:38 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118173

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 09/09/2024.

The direction update is issued at 1600 hrs 08/09/2024.

Manager NEM Real Time Operations
     
118174MARKET INTERVENTION07/09/2024 04:01:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118169

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/09/2024.

The direction update is issued at 1600 hrs 07/09/2024.

Manager NEM Real Time Operations
     
118173MARKET INTERVENTION07/09/2024 04:00:13 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118168

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/09/2024.

The direction update is issued at 1600 hrs 07/09/2024.

Manager NEM Real Time Operations
     
118171POWER SYSTEM EVENTS06/09/2024 08:18:58 PM

Update - Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 06/09/2024

Refer AEMO Electricity Market Notice 118166

At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
118169MARKET INTERVENTION06/09/2024 04:05:19 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118156

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/09/2024.

The direction update is issued at 1600 hrs 06/09/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm