[EventId:201] AP ENDED for ENERGY in NSW1 at 13 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 12 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116591 will end at 0400 hrs on 13 May 2024.
This is an AEMO autogenerated Market Notice.
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition - NEM regions.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 116572 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1115 hrs 13/05/2024.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 12/05/2024 10:54
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 116593
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 12/05/2024 09:53 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:201] AP STARTED for ENERGY in NSW1 at 12 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 12 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 12 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:200] AP ENDED for ENERGY in NSW1 at 12 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 11 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116581 will end at 0400 hrs on 12 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:200] AP STARTED for ENERGY in NSW1 at 11 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 11 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 11 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:199] AP ENDED for ENERGY in NSW1 at 11 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 10 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116570 will end at 0400 hrs on 11 May 2024.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Cancellation time: 10/05/2024 17:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 116578
Auto-generated on behalf of Manager NEM Real Time Operations