Filter by category
Filter by Date
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 28/05/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 28/05/2024
Refer Market Notice 116827
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs 31/05/2024
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 0930 hrs 31/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .
Manager NEM Real Time Operations
[EventId:202405311140_review] Prices for interval 31-May-2024 11:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311135_review] Prices for interval 31-May-2024 11:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311130_review] Prices for interval 31-May-2024 11:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1125 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311125_review] Prices for interval 31-May-2024 11:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1120 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311120_review] Prices for interval 31-May-2024 11:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1115 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311115_review] Prices for interval 31-May-2024 11:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1110 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Sheffield - Georgetown No. 2 220 kV line - TAS region - 30/05/2024
Inter-regional transfer limit variation -Sheffield - Georgetown No. 2 220 kV line - TAS region - 30/05/2024
At 2301 hrs 30/05/2024 there was an unplanned outage of Sheffield - Georgetown No. 2 220 kV line
The following constraint set(s) invoked at 2310 hrs 30/05/2024
T-GTSH
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations