Filter by category
Filter by Date
Update - Direction - SA Region - 18/12/2023
Update - Direction - SA Region - 18/12/2023
Refer Market Notice 112492
The AEMO intervention event that commenced from interval ending 1635 hrs on 18/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023
Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023
A planned outage of Palmerston - Hadspen 220 kV Line in the TAS region was scheduled from 1000 hrs 23/12/2023 to 1500 hrs 23/12/2023.
The outage has been completed and returned to service at 1045 hrs 23/12/2023
Constraint set(s) invoked:
T-HAPM_220
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V- MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
A planned outage of KEMPS CREEK No 2 525/345/34 kV Transformer in the NSW region was scheduled from 0600 hrs 23/12/2023 to 1200 hrs 23/12/2023.
The outage has been cancelled.
The following constraint set(s) invoked at 0600 hrs 23/12/2023
N-KC_TX
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
NSW1-QLD1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Direction - SA Region - 18/12/2023
Update - Direction - SA Region - 18/12/2023
Refer Market Notice 112584
The AEMO intervention event that commenced from interval ending 1635 hrs on 18/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
At 1300 hrs 22/12/2023 there was a short notice outage of Palmerston - Hadspen 2 220kV line.
Constraint set(s) invoked: T-HAPM_220
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V - MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Direction - SA Region - 18/12/2023
Update - Direction - SA Region - 18/12/2023
Refer Market Notice 112553
The AEMO intervention event that commenced from interval ending 1635 hrs on 18/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
[EventId:202312211310_review] Prices for interval 21-Dec-2023 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 21 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2023 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312211305_review] Prices for interval 21-Dec-2023 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 21 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2023 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312211300_review] Prices for interval 21-Dec-2023 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 21 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2023 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.