Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 18/12/2023 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
[EventId:202312171035_confirmed] Prices for interval 17-Dec-2023 10:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 17 December 2023
PRICES ARE NOW CONFIRMED for trading interval 17-Dec-2023 10:35.
In accordance with Market Notice 112435 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312171100_confirmed] Prices for interval 17-Dec-2023 11:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 17 December 2023
PRICES ARE NOW CONFIRMED for trading interval 17-Dec-2023 11:00.
In accordance with Market Notice 112441 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312171055_confirmed] Prices for interval 17-Dec-2023 10:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 17 December 2023
PRICES ARE NOW CONFIRMED for trading interval 17-Dec-2023 10:55.
In accordance with Market Notice 112440 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312171050_confirmed] Prices for interval 17-Dec-2023 10:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 17 December 2023
PRICES ARE NOW CONFIRMED for trading interval 17-Dec-2023 10:50.
In accordance with Market Notice 112439 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312171045_confirmed] Prices for interval 17-Dec-2023 10:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 17 December 2023
PRICES ARE NOW CONFIRMED for trading interval 17-Dec-2023 10:45.
In accordance with Market Notice 112438 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202312171040_confirmed] Prices for interval 17-Dec-2023 10:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 17 December 2023
PRICES ARE NOW CONFIRMED for trading interval 17-Dec-2023 10:40.
In accordance with Market Notice 112437 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0600 hrs 17/12/2023
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for return to service details
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023
Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023
At 0545 hrs 17/12/2023 there was a short notice outage of Sydney West - Vineyard No 29 330kV line.
Constraint set(s) invoked: N-SWVY_29
The following constraint set(s) invoked at 0545 hrs 17/12/2023
N-SWVY_29
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations