Market Notices

112209RESERVE NOTICE12/12/2023 03:04:17 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 112182 has been updated at 1400 hrs 12/12/2023 to the following:

From 1730 hrs to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 1285 MW.
The minimum capacity reserve available is 1193 MW.


AEMO Operations
112208RESERVE NOTICE12/12/2023 03:05:35 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112183 has been updated at 1400 hrs 12/12/2023 to the following:

From 2000 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1569 MW.


AEMO Operations
112201RECALL GEN CAPACITY12/12/2023 10:59:40 AM

Request for Generator Recall Information for 14/12/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112200RECALL GEN CAPACITY12/12/2023 11:01:01 AM

Request for Generator Recall Information for 14/12/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112187POWER SYSTEM EVENTS11/12/2023 04:04:48 PM

Update - Non-credible contingency event - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 11/12/2023

Refer AEMO Electricity Market Notice 112181

At 1554 hrs the remaining Mintaro - Waterloo 132 kV Line was returned to service.

The following constraint set(s) revoked:
S-X-MNWT+CB

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
112183RESERVE NOTICE11/12/2023 03:13:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112160 has been updated at 1400 hrs 11/12/2023 to the following:

From 1530 hrs to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 700 MW.


AEMO Operations
112182RESERVE NOTICE11/12/2023 03:12:58 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1700 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1287 MW.
The minimum capacity reserve available is 1019 MW.


AEMO Operations
112165POWER SYSTEM EVENTS11/12/2023 06:36:10 AM

Non-credible contingency event - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 11/12/2023

At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
112160RESERVE NOTICE10/12/2023 03:43:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023.

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112042 has been updated at 1530 hrs 10/12/2023 to the following:

From 1600 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1076 MW.


Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm