PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113601 has been updated at 1700 hrs to the following:
1.] From 1800 hrs 22/01/2024 to 1830 hrs 22/01/2024.
The forecast capacity reserve requirement is 1032 MW.
The minimum capacity reserve available is 995 MW.
[2.] From 1900 hrs 22/01/2024 to 1930 hrs 22/01/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 801 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113556 has been updated at 1400 hrs 22/01/2024 to the following:
From 1730 hrs to 2000 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113555 has been updated at 1400 hrs 22/01/2024 to the following:
From 1430 hrs to 2130 hrs 25/01/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 843 MW
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1700 hrs to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 1029 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2030 hrs 25/01/2024.
The forecast capacity reserve requirement is 1244 MW.
The minimum capacity reserve available is 1180 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113582 has been updated at 1100 hrs to the following:
[1.] From 1830 hrs 22/01/2024 to 2000 hrs 22/01/2024.
The forecast capacity reserve requirement is 1100 MW.
The minimum capacity reserve available is 690 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 22 January 2024
NON-CONFORMANCE VIC1 Region Monday, 22 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS4
Duration: 22/01/2024 04:15 to 22/01/2024 05:10
Amount: 27 MW
Constraint: NC-V_YWPS4
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202401212140_review] Prices for interval 21-Jan-2024 21:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 2135 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401212135_review] Prices for interval 21-Jan-2024 21:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 2130 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs